Hydrometallurgical Unit

Technology is invented, actual unit is under production.
Capacity: 500-800 kg/day/20 hour in case of gold coated copper parts,
In case of plastic parts 100-200 kg hence the size to weight ratio.

Space needed for the recycling unit: 10 m X 15 m 30mX60m closed workshop, minimum 4 meters of headroom, plus storage depending on capacity.
Required amount of electricity for the unit: 50 kW/h

The unit is semi-automatic.
Manufacturing time 120 days + 30 days fitting and testing.

Warranty: Factory engines: all- time warranty.
Wearing parts: depending on usage and maintenance.
Maintenance: Maintenance can only be executed by Replast System specialists or agreed partners.

Cooperation

Replast System representation technology is not for sale, we are only looking for partners for joint operation.